Haryana Vidyut Prasaran Nigam Limited (HVPNL) has started shifting two 66kV bays and associated electrical equipment at its Sector 33 substation in Gurugram to free land required for the proposed metro depot. The utility relocation, estimated to cost around INR 38 lakh, will make approximately 400 sq m available to Gurugram Metro Rail Limited (GMRL). The equipment currently obstructs the planned entry point linking the depot with the Millennium City Centre-Cyber City metro corridor. The shifting work has been allotted five months, although HVPNL officials are targeting completion by January. The proposed depot will cover around 53 acres in Sector 33 and has an estimated construction cost of INR 409 crore. The utility relocation is part of wider efforts to clear a 2.2-km stretch between Hero Honda Chowk and Umang Bharadwaj Chowk for Phase I of the metro corridor.
Haryana Vidyut Prasaran Nigam Limited (HVPNL) has started relocating two 66kV bays and associated electrical infrastructure at its Sector 33 substation in Gurugram to clear around 400 sq m of land required for the proposed Gurugram Metro Rail Limited (GMRL) depot. The work is being undertaken because the existing bays obstruct the planned entry point connecting the depot with the Millennium City Centre-Cyber City metro corridor.
The relocation involves shifting the two 66kV bays along with equipment such as circuit breakers and current transformers to another part of the substation. The work has been estimated at around INR 38 lakh and has been allotted five months. However, HVPNL is targeting completion earlier, with officials indicating that the shifting could be completed by January.
The utility work is part of the preparatory activities required to make the substation land available to GMRL. The proposed metro depot is planned across around 53 acres in Sector 33, with construction estimated to cost approximately INR 409 crore. GMRL has yet to finalise the agency for civil construction of the depot, pending approval from the state government.
The shifting is taking place alongside efforts to clear a 2.2-km stretch between Hero Honda Chowk and Umang Bharadwaj Chowk for metro construction. The section forms part of Phase I of the Cyber City metro corridor. NHAI, Dakshin Haryana Bijli Vitran Nigam Limited (DHBVNL) and HVPNL were directed last month to accelerate pending utility and infrastructure works and provide GMRL with a clear corridor for construction.
Several utility relocation activities remain pending along the stretch. NHAI is required to shift feeder lines, while a 1,600mm water pipeline and other utilities are yet to be relocated. HVPNL is also required to shift 66kV overhead lines, while DHBVNL has to relocate 17 feeders and dismantle existing lines. NHAI is additionally responsible for completing and commissioning the Sector 10 substation.
Meanwhile, civil construction of Phase I of the metro corridor, extending from Millennium City Centre to Sector 9, has progressed to around 15% completion. The 15.3-km phase is scheduled for completion in 2028 at an estimated cost of INR 1,277 crore.
The phase will include 14 elevated stations at Millennium City Centre, Sector 45, Cyber Park, Sector 47, Subhash Chowk, Sector 48, Sector 33, Hero Honda Chowk, Udyog Vihar 6, Sector 10, Sector 37, Basai and Sector 9. It will also include a spur connecting Basai with Sector 101 on Dwarka Expressway. The ongoing utility-shifting work at Sector 33 is therefore one of several preparatory activities required alongside construction of the wider metro corridor.