The Allahabad High Court has held that a homebuyer can claim interest for delayed possession even after accepting the flat. The ruling came in a dispute involving Antriksh Golf View in Sector 78, Noida, where possession was contractually due by November 2012 but was handed over more than four years later. The court also held that RERA does not prescribe a specific limitation period for claiming interest for delayed possession. It rejected the developer’s argument that restrictions linked to the Okhla Bird Sanctuary were responsible for the delay and upheld the interest payable to the homebuyer under the RERA Appellate Tribunal’s order.
The Allahabad High Court has ruled that accepting possession of a flat after a delay does not by itself prevent a homebuyer from claiming statutory interest for the period during which possession was delayed. The Lucknow bench made the observation while dismissing an appeal filed by Antriksh Developers and Promoters Pvt Ltd in a dispute involving its Antriksh Golf View project in Sector 78, Noida. The court also observed that the Real Estate (Regulation and Development) Act, 2016, does not prescribe a specific limitation period for an allottee seeking interest for delayed possession.
The case concerned homebuyer Shyam Sunder Agrawal, who booked a flat in the project in 2010. Under the agreement, possession was to be handed over by November 2012. The developer issued a final demand in April 2016 and physical possession was eventually given in May 2017. The court records also noted that the possession was offered without the occupancy certificate and other required documents. The occupancy certificate was obtained later.
The Uttar Pradesh Real Estate Appellate Tribunal had found that the project was delayed and that Agrawal remained entitled to interest even after taking possession. It directed the developer to pay interest on the amount deposited by the buyer from December 2012 until the date possession was handed over in May 2017. The interest was to be calculated at one percentage point above the Marginal Cost of Fund Based Lending Rate, or MCLR.
Antriksh Developers challenged the order before the High Court and argued that the delay was linked to restrictions imposed by the National Green Tribunal concerning construction and the grant of occupancy certificates within a 10-km radius of the Okhla Bird Sanctuary. The developer sought to rely on the period covered by those restrictions while contesting the interest liability.
The High Court did not accept the argument as a basis for removing the entire period of delay. The bench noted that the developer's own case was that the project had been completed in 2014 and that an application for the occupancy certificate had also been made that year. The court held that the developer could not simultaneously maintain that the project had been completed and that the NGT restriction had prevented its completion.
The timing of the restriction was also important. The NGT restriction came into effect in August 2013, while the contractual deadline for handing over the flat was November 2012. The court therefore held that the developer's default had already occurred before the restriction came into force. It also observed that the “zero period” recognised in connection with the NGT restrictions could apply only to the period during which the project was actually affected and could not erase a delay that had occurred before the restriction.
The High Court also dealt with the question of whether a homebuyer who continued with the project and accepted possession could later seek interest. Referring to Section 18(1) of RERA, the court noted that an allottee who continues with the project is entitled to interest for every month of delay until possession is handed over. The court found no specific limitation period under the provision for such a claim and held that the buyer's claim remained maintainable even after possession had been taken.
The court consequently dismissed the developer's appeal and left the direction to pay delayed-possession interest undisturbed. The ruling means that, in this case, taking possession did not amount to giving up the buyer's statutory claim for interest for the period of delay. The judgment, however, turned on the contractual possession date, the circumstances surrounding the delay and the regulatory restrictions relied upon by the developer.
Source PTI