The Surat-Vapi section of the Mumbai-Ahmedabad bullet train project is likely to open by mid-2027, Railway Minister Ashwini Vaishnaw said, with the initial Surat-Bilimora stretch opening first. He said the Thane-Ahmedabad section is targeted for 2028 completion, with the full 508-km corridor operational by 2029, cutting Mumbai-Ahmedabad travel time to around two hours. More than 85 per cent of elevated viaduct work is complete, along with 17 of 25 planned river bridges and 560 track-km of reinforced concrete track bed, the minister said.
The Surat-Vapi section of the Mumbai-Ahmedabad bullet train project is likely to open by mid-2027, Railway Minister Ashwini Vaishnaw said, as construction on India's first high-speed rail corridor continues to progress in phases.
Vaishnaw said overall progress on the 508-km Mumbai-Ahmedabad High-Speed Rail corridor remains strong, with the initial commercial stretch between Surat and Bilimora, spanning around 50 km, expected to open first, followed by the extension to Vapi. He said the project would be commissioned in stages rather than as a single opening: the Thane-Ahmedabad section is targeted for completion by 2028, with the entire Mumbai-Ahmedabad line expected to become fully operational by 2029. Once complete, the corridor is expected to cut travel time between Mumbai and Ahmedabad to around two hours and seven minutes, compared with roughly seven to eight hours currently by road.
The Minister said heavy construction work at Surat station, one of the 12 stations planned along the corridor, has been completed, with finishing and utility works now progressing alongside track-linking activity. He highlighted the use of modern safety features built into the corridor, including vibration-absorption mechanisms along the track and design elements intended to withstand high winds and seismic activity, and said the main line has been designed for speeds of up to 320 kmph, with a lower design speed of 80 kmph for loop sections near stations.
The 508-km corridor, being developed using Japanese Shinkansen high-speed rail technology, runs across Gujarat, Dadra and Nagar Haveli, and Maharashtra, connecting major cities including Ahmedabad, Vadodara, Bharuch, Surat, Vapi, Thane and Mumbai. According to project data cited alongside the Minister's remarks, more than 85 per cent of the corridor's elevated viaduct sections have been completed, along with 330 km of viaducts and 408 km of piers, while 17 of the corridor's 25 planned river bridges have been finished. Track-bed work using reinforced concrete has been completed across 560 track-km, and noise barriers spanning 235 km have been installed at various points along the route.
Vaishnaw's remarks come as the government continues to position the bullet train project as a flagship infrastructure initiative, with construction work having begun in April 2021 and phased commissioning now expected to extend through the end of the decade as remaining sections, including undersea tunnelling work in the Mumbai metropolitan region, are completed. Among the specific milestones the ministry has flagged in recent months is the breakthrough of a roughly 1.5-km tunnel connecting Virar and Boisar in Palghar, Maharashtra, one of seven mountain tunnels planned for the corridor alongside a single undersea tunnel, work on which continues in the Bandra Kurla Complex-Shilphata stretch nearer Mumbai. Vaishnaw has previously said the bullet train, once operational, is intended to function as an affordable and convenient mode of transport for the middle class, drawing a comparison with the economic transformation that followed the introduction of Japan's first Shinkansen line.
Source: NHSRCL's YouTube