The Haryana Real Estate Regulatory Authority (HRERA), Gurugram, has directed Ocus Skyscrapers Realty to pay 10.8% annual interest to commercial unit buyer Archana Dubey over a seven-month delay in handing over possession at Ocus 24K in Sector 68. The authority found that the developer failed to meet the possession deadline under the buyer’s agreement and ordered payment of interest on the amount paid by the buyer. It also directed the developer to execute the conveyance deed within three months and barred it from imposing charges outside the original buyer’s agreement. Several allegations concerning the allotment and statutory approvals were not accepted by HRERA.
The Haryana Real Estate Regulatory Authority has ordered Ocus Skyscrapers Realty to pay delayed-possession interest to a Gurugram resident in connection with its commercial project Ocus 24K in Sector 68. The authority directed the developer to pay interest at 10.8% per annum to Archana Dubey and clear the arrears within 90 days.
Dubey, a Sector 46 resident, had booked commercial unit G-119, measuring 419 square feet, in Ocus 24K. Under the buyer’s agreement, the developer was required to hand over possession within 60 months. The contractual possession deadline was therefore December 2018. However, the occupation certificate was issued in July 2019 and possession was formally offered the following day, resulting in a delay of around seven months.
HRERA found Ocus Skyscrapers Realty in breach of Section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016, for failing to hand over possession within the agreed period. Applying Section 18(1) of the Act along with Rule 15 of the HRERA Rules, the authority ordered interest at the prescribed rate of 10.8% per annum. The rate was calculated based on the State Bank of India’s marginal cost of lending rate plus 2%.
The interest was directed to be calculated on the amount paid by Dubey from the contractual possession due date until September 2019. The calculation also took into account the two-month period following the offer of possession, in line with Section 19(10) of the RERA Act.
The authority also directed Ocus Skyscrapers Realty to execute the conveyance deed within three months. It further barred the developer from imposing any charges that were not covered by the original buyer’s agreement. The interest arrears were ordered to be cleared within 90 days.
The complaint also involved allegations concerning the allotment of two commercial units. Dubey had another unit, G-215, in the developer’s Ocus Medley project in Sector 99. She alleged that the two units had been wrongly conflated to divert funds and alter her allotment without her consent.
HRERA did not accept this allegation. The authority accepted the developer’s position that G-215 in Ocus Medley and G-119 in Ocus 24K belonged to separate, independently registered projects. The authority also rejected the buyer’s plea concerning limitation on this particular ground, while continuing to examine her delayed-possession claim on its merits.
Dubey had also raised allegations regarding the alleged fraudulent procurement of the occupation and completion certificates. She further claimed that the project remained incomplete and that construction debris was present at the site. HRERA did not adjudicate these issues, holding that they fell outside its jurisdiction. The authority directed her to approach the director of town and country planning or a competent civil court for these matters.
Ocus 24K is a registered commercial project in Sector 68, Gurugram, promoted by Ocus Skyscrapers Realty. HRERA records show that the project was registered under registration number 220 of 2017, with its location listed as Village Badshahpur, Sector 68.
The order adds to the record of possession-related disputes involving real estate projects in Gurugram, where HRERA has considered delayed handover claims under the statutory interest provisions of RERA. In this case, however, the relief was limited to the possession delay and related contractual directions, while the other allegations were left to the appropriate forums.