The Haryana Real Estate Regulatory Authority (HRERA), Gurugram, has passed an order in a complaint filed by Archana Dubey against Ocus Skyscrapers Realty Ltd over delayed possession of a commercial unit in the Ocus 24K project in Sector 68. The authority directed the developer to pay interest at 10.80 per cent per annum for the period between the due date of possession and the eventual offer of possession, and to execute the conveyance deed within three months. Allegations of a fraudulently switched allotment and irregularities in the occupation certificate were left for other forums to examine, while the possession and maintenance-related claims were dealt with within HRERA's own jurisdiction.
HRERA Gurugram, headed by Chairman Arun Kumar, last month disposed of a complaint filed by Archana Dubey, represented by her brother and authorised representative Shishir Dubey, against Ocus Skyscrapers Realty Ltd, the promoter of the Ocus 24K commercial project in Sector 68, Gurugram.
The complainant had booked unit G-119, admeasuring 419 square feet on the ground floor, in the project, which carries DTCP licence number 76 of 2012 and was registered with HRERA under registration number 220 of 2017. The builder-buyer agreement for the unit was signed in December 2013, with a total sale consideration of INR 60,95,402. As per the agreement, the developer had committed to completing construction within 60 months of the agreement, placing the due date of possession at December 16, 2018.
The complainant told the authority that she had originally booked a different unit, G-215, measuring 479 square feet, and alleged that the developer had unilaterally switched her allotment to G-119 without her consent, while failing to adjust roughly INR 7.4 lakh she had already paid toward the earlier unit. She said her father, who was elderly and unwell at the time, had been handling the transactions and had complied with the developer's demands without realising the change. She also claimed she was overcharged by around INR 6.64 lakh beyond the agreed sale price and alleged that the occupation certificate, granted in July 2019, and the completion certificate, issued in July 2023, were obtained through misrepresentation, since construction work and debris were reportedly still visible at the site.
The developer countered that G-215 belonged to an entirely separate project, Ocus Medley in Sector 99, and had no connection to the Ocus 24K unit in question. It also argued that the complaint was time-barred, having been filed nearly nine months after the three-year limitation period lapsed, and stated that the complainant had defaulted repeatedly on payments and had already taken physical possession of the unit in May 2022, using it to run a tea shop, without raising any objection at the time. The developer further said the complainant now owed over INR 3 lakh in unpaid maintenance and over INR 58,000 in outstanding electricity charges.
After reviewing the submitted documents, the authority found the developer had indeed breached its obligations under Section 11(4)(a) of the RERA Act by failing to hand over possession on time. It calculated the delay period from the due date of December 16, 2018, to the date of offer of possession plus a two-month grace period, ending September 18, 2019, and directed that interest at the State Bank of India's marginal cost of lending rate plus two per cent, currently 10.80 per cent per annum, be paid for this period. The arrears must be cleared within 90 days, placing the deadline around mid-October this year. The authority also ordered the developer to issue an updated statement of account within 30 days and to execute the conveyance deed in the complainant's favour within three months, subject to applicable stamp duty and registration charges.
On the question of maintenance, the authority referred to an earlier ruling and held that developers cannot charge maintenance for more than a year in cases where the agreement lacks a specific clause. However, it declined to intervene on the broader claims regarding incomplete construction and the alleged fraudulent procurement of the occupation certificate, stating these fell outside its jurisdiction and advising the complainant to approach the Director of Town and Country Planning or a civil court instead.
Source Haryana RERA