SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Bombay High Court clears construction on two Pune Cantonment leasehold plots

#Law & Policy#Land#India#Maharashtra#Pune
Synopsis

The Bombay High Court has cleared the way for residential construction on two leasehold plots in Pune Cantonment near the Headquarters of Southern Command, setting aside orders by the Pune Cantonment Board and defence authorities that had rejected the leaseholders' building proposals. A Division Bench of Acting Chief Justice Ravindra V. Ghuge and Justice Gautam A. Ankhad held that a mere apprehension that construction might complicate the land's future resumption by the government cannot defeat rights presently subsisting under a valid, renewed lease. The court rejected both the Army's security objections and its claim that the land was needed for Officers' Married Accommodation, finding no concrete project or timeline had been placed on record to support either concern.

The Bombay High Court has set aside orders by the Pune Cantonment Board (PCB) and defence authorities rejecting residential construction proposals on two leasehold plots at Queen's Garden, Pune Cantonment, clearing the way for three civilian leaseholders to build bungalows on land located close to the Headquarters of Southern Command. 
A Division Bench comprising Acting Chief Justice Ravindra V. Ghuge and Justice Gautam A. Ankhad, ruling on writ petitions filed by Nikhil Vithal Jhaveri and Kirti V. Jhaveri, and separately by Mamta Jain, held that an apprehension about future difficulties in resuming defence land cannot override rights that are presently valid and subsisting under a renewed lease. The judgment was reserved on 2 September and pronounced on 7 September. 
The petitioners hold leasehold rights over plots forming part of a larger parcel of defence land originally leased in 1944, under an Indenture of Lease covering approximately 3.10 acres, granted for an initial 30 years and renewable up to an aggregate 90-year term. The parcel was later subdivided into four plots through assignments and partition proceedings. The current lease term, renewed in 2007, subsists until 30 November 2033. 
In 2020 and 2022, the respective petitioners had applied for permission to construct residential bungalows on their plots under Section 235 of the Cantonments Act, 2006. The applications remained pending for years before being rejected in March 2025, after the Government, acting through the General Officer Commanding-in-Chief, withheld its consent and an objection was raised under Section 238(3) of the Act. This followed nearly two decades of correspondence with the Defence Estate Office and representations to the Ministry of Defence, during which administrative inaction had led one petitioner to approach the Delhi High Court in 2024. 
Defence authorities had argued before the Bombay High Court that Pune was a land-deficient station facing an acute shortage of Officers' Married Accommodation, and that permanent construction near the Southern Command Headquarters — which had served as a staging area during Operation Sindoor — could raise security concerns, complicate future resumption of the land, and create financial liability for the government over construction costs. 
The Bench rejected these objections, finding that no concrete, sanctioned project, identified commencement date or immediate plan for utilising the specific plots had been placed on record, despite the requirement having been asserted for over two decades. The court noted that a general assertion of future requirement could not be treated as an immediate operational need. On the security-related objections tied to the land's proximity to Southern Command Headquarters, the Bench found no identified defence activity that the proposed construction would interfere with. 
The court observed that the respondents had not pointed to any provision of the subsisting lease or applicable building regulation that prohibited the construction, and that an apprehension about future resumption difficulty could not by itself justify defeating a presently subsisting contractual and statutory right. It further noted that once a claim of unequal treatment was raised, the State was required to furnish a rational basis for differential treatment between plots, and that a reference to an audit objection concerning a separate plot did not adequately explain such a distinction. 
During the hearing, the petitioners furnished undertakings to the court, recorded in an order dated 20 January 2026, addressing the government's concerns around future use, third-party rights and compensation claims — including a waiver of ex-gratia compensation should the land be resumed by the Army after the lease expires in 2033, and a bar on creating third-party development rights. The court held that these undertakings adequately addressed the government's stated concerns regarding eventual resumption of the land. 
The Bench clarified that the grant of construction permission would not confer any right to renewal of the lease beyond 30 November 2033, nor entitle the petitioners to claim any equity on account of the construction undertaken. The matter has been listed for recording compliance on 23 October 2026. 
Source: Bombay High Court