State-run NBCC Ltd's efforts to complete 16 stalled Supertech housing projects remain constrained by unresolved regulatory hurdles and a funding gap, even as the company moves toward awarding construction contracts. NBCC has petitioned the Supreme Court seeking relief from certain RERA compliance requirements after the National Company Law Appellate Tribunal refused to grant such exemptions, with the matter listed for hearing on 24 September. The company estimates it needs fresh investment of around INR 1,700 crore against projected receivables of INR 2,200 crore from homebuyers to complete the sold units across the projects, which together comprise nearly 50,000 residential units in Noida, Greater Noida and other locations.
NBCC (India) Ltd's court-directed effort to complete 16 long-stalled residential projects of insolvent developer Supertech Ltd continues to face both legal and financial constraints, even as the state-owned construction company moves toward awarding construction contracts for the developments.
NBCC has approached the Supreme Court challenging a National Company Law Appellate Tribunal (NCLAT) order dated 22 May that refused to exempt the company from certain statutory requirements under the Real Estate (Regulation and Development) Act (RERA) while completing the projects. A bench headed by Chief Justice Surya Kant, along with Justices Joymalya Bagchi and V. Mohana, issued notice on NBCC's petition and listed the matter for hearing on 24 September. The NCLAT had held that it lacked jurisdiction to waive statutory requirements, stating instead that it had already directed the relevant regulatory authorities to process NBCC's required approvals within specified timelines.
Among the relaxations NBCC is seeking is relief from RERA's requirement that 70 per cent of funds collected from homebuyers for each registered project be held in a separate escrow account specific to that project. NBCC has argued that this restriction makes it difficult to complete the Supertech projects because the 16 developments are at different stages of construction and have different funding positions, and the company wants to deploy surplus collections from financially stronger projects toward those that have run out of funds. NBCC has also sought relief from the requirement to obtain prior consent from allottees before a majority of the promoter's rights and liabilities can be transferred to a third party.
On the funding side, NBCC has estimated that completing the units already sold across the 16 projects would require fresh investment of around INR 1,700 crore, against projected receivables of approximately INR 2,200 crore from homebuyers. Depending on the stage of construction, the company has indicated that delivery could take around one year for more advanced projects and up to three years for developments where construction has barely begun.
Speaking at the company's first-quarter earnings call on 12 August, NBCC chairman and managing director K.P. Mahadevaswamy said consultants had been appointed across all the Supertech projects and were finalising the quantities of work still required for completion. He said NBCC expected to float and finalise tenders during the current quarter, with revenue from the projects expected to begin flowing from the following quarter. Mahadevaswamy said NBCC expects to award contracts worth INR 20,000–25,000 crore during the current financial year overall, of which around INR 10,000 crore would relate specifically to the Supertech projects. He attributed the earlier delay in starting work to litigation, saying the company had by then received the clearance it needed from the Supreme Court to proceed with tendering.
NBCC was brought into the Supertech insolvency process by an NCLAT order dated 12 December 2024, which directed the state-run company to complete the stalled projects in the interest of homebuyers. That order was subsequently challenged before the Supreme Court, which upheld NBCC's appointment, holding that bringing the company in to complete the projects was neither unfair nor contrary to the Insolvency and Bankruptcy Code. The NCLAT's December 2024 order had also made clear that NBCC would need to comply with statutory requirements, including under RERA — the compliance issue now before the Supreme Court.
Supertech was admitted into insolvency proceedings following a petition filed by Union Bank of India. The 16 projects assigned to NBCC comprise close to 50,000 residential units located in Noida, Greater Noida and other areas, a substantial share of which have been sold to homebuyers but remain undelivered. NBCC has pointed to its experience managing the previously stalled Amrapali projects, where the Supreme Court cancelled the developer's RERA registration and appointed NBCC as project management consultant, as a model for how the Supertech developments could be completed; Mahadevaswamy said NBCC earns an 8 per cent project management fee and a 1 per cent marketing fee on the Amrapali projects.
The Supreme Court's 24 September hearing is expected to determine whether NBCC receives the additional financial flexibility it says is necessary to move funds across the 16 projects and accelerate construction.