SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Supreme Court clears path for Sushant Aquapolis resolution plan, relief for 1,600 buyers

#Law & Policy#Residential#India
Synopsis

The Supreme Court has cleared the way for implementation of the resolution plan for the stalled Sushant Aquapolis housing project in Ghaziabad, accepting a proposal from the Successful Resolution Applicant to develop a 24-metre-wide pathway on three boundaries of the project site without claiming title over the land. The order follows an earlier direction in July requiring the Uttar Pradesh government and Ghaziabad Development Authority to resolve pending approvals, offering relief to nearly 1,600 homebuyers who have awaited possession for close to two decades.

The Supreme Court has cleared the path for implementation of the resolution plan for the stalled Sushant Aquapolis housing project in Ghaziabad, offering relief to nearly 1,600 homebuyers who have been awaiting possession of their flats for close to two decades. 
In an order dated 31 August, a bench of Justices J.B. Pardiwala and K. Vinod Chandran, hearing Civil Appeal No. 4473 of 2026 filed by One City Infrastructure Private Limited against the Ghaziabad Development Authority, accepted a proposal from the Successful Resolution Applicant to develop a 24-metre-wide pathway along three boundaries of the project plot, designated GH-1, without asserting any claim of title over that land. The order permits the applicant, or its assignees, to carry out this development and subsequently make the necessary applications to the Ghaziabad Development Authority to unlock implementation of the resolution plan. The bench described the project, which was promoted as a group housing cluster by the corporate debtor M/s Ansal Urban Condominium Private Limited, as having faced multiple difficulties in the course of the resolution process. 
The 99-acre township was originally allotted to Ansal Properties & Infrastructure Limited, with the development licence for the land continuing to be held in the name of the original developer rather than the Successful Resolution Applicant. Of the total area, development had already taken place on 26 acres, with the remaining portion under the Ghaziabad Development Authority's possession and earmarked for separate future development. The authority acknowledged that residential towers had come up on the developed portion but described their condition as dilapidated, underscoring the extent of construction delays the project had faced since it stalled. 
The order builds on a more comprehensive interim direction the Court had passed on 30 July, in which it directed the Uttar Pradesh state government and the Ghaziabad Development Authority to consult with each other and arrive at a final decision within two weeks on renewal of the development licence and approval of the project's revised building plans. In that earlier hearing, the bench had also directed the Vice-Chairman of the Ghaziabad Development Authority and the state's Principal Secretary, Housing, to carry out a thorough inspection of the site, and had criticised the authorities for what it described as inaction that had left homebuyers waiting nearly 19 years for possession of their flats. The state government had told the Court that the authority required guidance on whether the revised building plans could be approved, who would be responsible for developing common infrastructure, and whether the original developer or the Successful Resolution Applicant would bear responsibility for constructing housing for economically weaker sections and lower income groups. 
Pursuant to those July directions, the Ghaziabad Development Authority filed an affidavit on 19 August outlining an action plan, stating that it had disposed of the applicant's representation, provided guidance under the integrated township policy, and would sanction the building plan upon receipt of an online application, while keeping the interests of homebuyers in view. 
At the 31 August hearing, the Successful Resolution Applicant raised the absence of proper access to the project site as an outstanding obstacle to implementation. The authority produced a map indicating an existing 24-metre-wide road running around three sides of the property, though the applicant submitted that this road was non-functional owing to a lack of maintenance and undertook to reconstruct it. The Court's latest order addresses this access issue through the pathway arrangement, without disturbing questions of title over the land. The resolution plan for the project had earlier been approved under Section 31 of the Insolvency and Bankruptcy Code, 2016, but its implementation had remained stalled pending the licensing and access issues now addressed by the Court's successive orders. 
Source- India Kanoon