SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Pune rail works to disrupt 67 train services from September 19 to October 4

#Infrastructure News#Infrastructure#India#Maharashtra#Pune
Synopsis

Railway services in Pune will face major disruptions between September 19 and October 4 as Central Railway undertakes a 15-day mega infrastructure block to commission the third railway line between Hadapsar and Ghorpadi Coach Maintenance Complex. The works will affect 67 train services, including 42 cancellations and 25 diversions, along with short terminations, revised schedules and changes to suburban and DEMU services. The phased block coincides with the Ganeshotsav period and is part of a wider capacity enhancement programme aimed at improving operational efficiency and safety.

Railway operations in Pune will undergo significant disruption from September 19 to October 4 as Central Railway carries out a 15-day mega infrastructure block to commission the third railway line between Hadapsar and the Ghorpadi Coach Maintenance Complex (GCMC). The project involves engineering, signalling, telecommunication and overhead equipment works at the Pune and Hadapsar yards, making several railway lines temporarily unavailable. 
The block will affect 67 train services, with 42 trains cancelled and 25 trains diverted during the period. In addition, several services will face short terminations, short originations, rescheduling and revised operating timings, affecting long-distance mail and express trains as well as suburban and DEMU services operating through the Pune division. 
The disruption will coincide with the Ganeshotsav travel period, when passenger volumes are expected to be significantly higher. Railway authorities have advised passengers to verify train schedules and operational changes before travelling, as multiple services connecting Pune with destinations across Maharashtra and other states will be affected. 
The phased traffic block has been planned to facilitate critical infrastructure works required for the third-line project. During the initial phase, from September 19 to September 23, both the up and down main lines between Pune and Hadapsar will remain blocked daily from 12 noon to 5 pm, with the duration of subsequent blocks gradually reducing as construction progresses. 
Several prominent train services, including Pune-Solapur, Nagpur-Pune, CSMT-Pune, Kolhapur-Pune and multiple Daund, Baramati, Satara and suburban DEMU services, feature among the affected trains. Some long-distance services will operate through diverted routes via Daund, Ahilyanagar, Manmad, Igatpuri, Kalyan, Miraj and Kurduwadi, depending on the scheduled date of operation. 
The infrastructure works form part of Central Railway's broader capacity enhancement programme for the Pune division. The commissioning of the third line is expected to improve operational flexibility, reduce congestion, enhance safety through upgraded signalling systems and support the handling of additional train services in the future.

Discussion

Have something to say? Post your comment