The Supreme Court has raised concerns over deviations from the original plan of DLF's "The Primus" project in Sector 82A, Gurugram, after examining a CBI status report. A 24-metre-wide access road shown in the project's brochure does not exist along a 147-metre stretch, which is instead used for landscaping and parking. A bench of Justices Ahsanuddin Amanullah and R. Mahadevan said the deviation was not minor and warned of further orders if it is not corrected.
The Supreme Court has raised concerns over substantial deviations from the original plan of DLF's "The Primus DLF Garden City" project in Sector 82A, Gurugram, after examining a status report submitted by the Central Bureau of Investigation on the project's disputed access road.
A bench of Justices Ahsanuddin Amanullah and R. Mahadevan examined the original brochure, maps, photographs and the CBI's report, and found that a 24-metre-wide road shown in the layout plan does not exist in its represented form along a 147-metre stretch, where the designated area is instead used for landscaping and parking. The court said the comparison left no doubt that the project was not in conformity with what was shown to buyers, and questioned why the deviation had not been rectified despite the developer earlier being given opportunities to do so.
The dispute traces back to May 2012, when DLF marketed The Primus as a premium complex featuring two 24-metre sector access roads, banquet facilities, tennis courts and swimming pools. Homebuyers booked apartments in August 2012, with an agreement signed in December 2012 promising possession by 28 February 2016. By that deadline, buyers had paid nearly 95 per cent of the cost, but the project remained incomplete, with only a Partial Occupation Certificate issued on 7 October 2016 and, according to buyers, no permanent water or electricity connections.
Aggrieved buyers approached the National Consumer Disputes Redressal Commission, where it emerged the road had reportedly been built on private agricultural land belonging to farmers. The matter reached the Supreme Court through appeals in Swarnpreet Kaur & Anr. v. DLF Home Developers Ltd. & Ors.
In an earlier order dated 25 February 2026, the same bench had directed a CBI inquiry into the alleged irregularities. The court had said it was "hard-pressed to reckon" the case was a one-off incident, describing the issues flagged by buyers as possibly "just the tip of the proverbial iceberg" within the organised real estate sector, and noting concern for ordinary consumers who often invest their life savings in a single home toward the end of their careers. It had directed any person or authority required to assist the CBI to do so, asked the agency to submit findings by 25 April 2026, and requested Additional Solicitor General S.V. Raju to assist the court.
Following the CBI's status report, the court has now directed the CBI Director to assign two additional inspectors to expedite the inquiry, and said it expects to review whether the deviations have been addressed by the next hearing, warning it may pass further orders if the project is not brought into conformity.
DLF Limited has previously stated in regulatory filings that the matter involves its subsidiary and remains under legal consideration, maintaining the project was delivered in accordance with the required occupancy certificate.
The case turns on whether brochures and site plans shown to buyers at booking carry legal weight, or whether they can be treated as illustrative marketing material subject to later change, a question with relevance for disputes across the industry involving promised amenities and layouts that differ from what is ultimately delivered. The report did not specify the next hearing date, nor the remedial steps DLF is expected to undertake to bring the project into conformity with its original plan.