SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Pune’s Talegaon-Chakan-Shikrapur road gets urgent repair deadlines amid monsoon damage

#Infrastructure News#Infrastructure#India#Maharashtra#Pune
Synopsis

The Maharashtra Public Works Department has accelerated repairs on the 54-km Talegaon-Chakan-Shikrapur road in Pune, with officials directed to restore a comparatively less-damaged 40-km stretch within two days and repair the severely damaged 14-km MIDC section within four days. The industrial corridor has deteriorated significantly during the monsoon, affecting motorists and freight movement. The state has sanctioned INR 59 crore for repairs and partial widening, with work orders issued in January 2026. Progress was slowed by utility-shifting issues and difficulties in sourcing bitumen amid global supply disruptions. Separately, around 12 km of the corridor is planned for widening over the next two months, while Maharashtra State Infrastructure Development Corporation (MSIDC) is expected to undertake a longer-term upgrade of the entire corridor.

The Maharashtra Public Works Department (PWD) has been directed to accelerate repairs on the 54-km Talegaon-Chakan-Shikrapur road in Pune, with 40 km to be restored within two days and the more severely damaged 14-km MIDC section to be repaired within four days. The instructions were issued by Public Works Minister Shivendrasinhraje Bhosale on Friday, Aug 28, following a review of the deteriorated industrial and traffic corridor. 
The road has suffered extensive deterioration during the monsoon, creating difficulties for motorists and affecting movement along an important industrial corridor connecting Talegaon, Chakan and Shikrapur. Of the total 54-km stretch, around 40 km has sustained comparatively less damage, while the remaining 14 km within the MIDC area is in significantly poorer condition. 
Under the immediate repair programme, the PWD has been instructed to fill potholes, restore road shoulders and undertake necessary filling and other restoration work. The department is working to complete repairs to the 40-km section within two days, while the more damaged 14-km stretch has been given a four-day deadline. 
The state government had sanctioned INR 59 crore for repairs and partial widening of the corridor. Work orders were issued in January 2026 and repair work had begun on some sections. However, progress was affected by difficulties associated with shifting utility lines along the road and challenges in procuring bitumen amid global supply disruptions. The deterioration of the road during the monsoon has now prompted the department to accelerate the work. 
The government had earlier decided that the PWD would undertake repairs on the corridor for one year instead of the National Highways Authority of India (NHAI), citing the urgency of the work and experience from the previous year. The road is a significant route for industrial traffic because of the concentration of manufacturing and logistics activity around the Chakan-Talegaon MIDC belt. 
Alongside the immediate repairs, the government has planned widening of approximately 12 km of the corridor over the next two months to respond to increasing traffic volumes. The widening is separate from the immediate pothole-filling and restoration work being undertaken by the PWD. 
A longer-term upgrade of the entire Talegaon-Chakan-Shikrapur corridor is also planned through the Maharashtra State Infrastructure Development Corporation (MSIDC). Work on this upgrade is expected to begin within the next three months. The proposed intervention is intended to increase the corridor’s traffic-handling capacity and address recurring congestion and road deterioration. 
Bhosale has been reviewing the condition of the road and has instructed officials to complete the immediate restoration works within the prescribed deadlines. The accelerated repair programme is intended to address the current monsoon-related deterioration while the planned widening and longer-term upgrade provide separate measures for the corridor’s capacity and infrastructure requirements. 
The three-stage approach — immediate repairs, widening of around 12 km and a broader MSIDC-led upgrade — comes as traffic demand continues to increase along the industrial route. For now, the PWD has been given tightly defined deadlines to restore the existing carriageway and improve conditions on the most damaged sections.